Danville-Riverside Bridge
Preservation Work Resumes This Week
Montoursville –
Preservation work on the (Route 54) Danville-Riverside Bridge in Montour and
Northumberland counties will resume this week.
The work planned on the
1,440’-long bridge over the North Branch Susquehanna River is scheduled to
resume this Thursday, Aug. 8, pending favorable weather.
The work for this phase of
construction is the epoxy and stone-chip overlay of the bridge deck.
Prime contractor HRI Inc. will be
using daylight traffic control starting at 7 a.m. daily. The contractor will
maintain two lanes of traffic and put the traffic signals on flash while
flagging personnel maintain traffic movements.
The epoxy overlay work is
scheduled to take nine working days.
This is part of a five-bridge,
$1.3 million contract begun in April and scheduled for completion by August
9.